Description The Huntley Bridge was one of five in West Prince that washed out during heavy flooding on December 2014.
Project Details: The bridge was constructed using a 200 mm cast-in-place deck slab over pre-cast pre-stressed NEXT F Beams with partial-depth flanges serve as formwork. The beams were simply supported over a single span of 20 m.
Owner: Ministry of Transportation, PEI
Engineers: WSP Parsons Brinckerhoff Engineering Services TUF-BAR Product Used: TUF-BAR, 60 GPa (Grade III) Deck: # 5 (15M) and # 6 (20M). A total of 6200 m. Wing walls: # 5 (15M). A total of 700 m.